Sydney Airport Third Runway
Client
Baulderstone Hornibrook Pty Ltd (Leighton Contractors), Sydney NSW
​
Project Goal
Sydney Airport decided to build additional 3rd runway parallel to original runway in Botany Bay.
​
Budget
$500 million
​
Delivery
Construction of Airport Third Runway (new runway)
​
Scope of Services Project Planner Planning Engineer consulting contractor:
-
Construction of Sydney Airport Third Runway
-
Scheduling/Planning and Development of Standard Construction Schedules, as build schedules
-
Development and control of QA system for monitoring pavement construction of Runway all Taxiways and Access Roads
-
Mentoring and training of Engineering staff.
Javelin Associates is quick and responsive. Their work put more light into complex issues of our project planning
Lawrence Gatton, Deputy Program Manager, Lockheed Martin