Toka Tindung Gold Processing Plant
Client
MacDow Indonesia
​
Project Goal
1st Pour Gold, April 2011
​
Budget
$36 million
Delivery
1 April 2011
​
Toka Tindung Gold Processing Plant
This construction project in North Sulawesi Island in Indonesia was completed within time schedule and budget.
​
Project scope
Our scope was to develop, maintain and control projects master schedule and report progress to project manager and client stakeholders. The master programme held resources and was balanced to reflect usage efficiency. Programme was updated weekly and reported directly to project team and management.
​
Good Day, Have attached a press release from London's AR Stock Market announcing that the Toka Tindung Gold Mine has commenced to Pour Gold. This was achieved on Friday night 1 Apr 2011 at around 8pm. The Project has been a very successful one and I would like to take this opportunity in thanking you for your contribution, your time and assistance, and I look forward to hopefully working with you in the future. Kind Regards,